Feeding in Prep
Process:
The feeding station on Prep line #1 and line #2
Definitions:
Procedure:
-
Pull the next frame out of the rack and check for any of the following options:
- WS (wood on sill)
- Gold label certification (indicated by the two letters before the invoice)
- Window type (SH, SV, DV, PW, PM, etc.)
- Orientation of vent (left or right)
- Window color (DW, DK, DT, DA, DQ, etc.)
- If the frame had WS (wood on sill) or NC (noncertified) for its gold label certification indicator, call this out to the other line members.
-
Bring the frame to the line's staging location and install the needed hardware.
-
For SH frames.
- Install a spring clip and spring into each jamb.
- Install two shipping blocks into the inner sill of the frame about 1” from the edge.
-
For SV frames.
- Install two anti-lift blocks into the inner head of the frame, only on the vent portion of the frame.
- Using a pair of cutters, install the track onto the inner sill of the frame.
-
For DV frames.
- Install four anti-lift blocks into the inner head of the frame. Spread the anti-lift blocks out so two are placed on each vent portion of the frame.
- Using a pair of cutters, install the track onto the inner sill of the frame.
-
For SH frames.
- Place the frame onto the prep line.
- Place the frame’s mullion inside the frame. Make sure to orient the mullion correctly when placing it into the frame.